Bills of materials

A bill of materials (BOM) lists the components of a product. Each change is a revision.

Before you start

You need build.engineering.manage.

Steps

  1. Open Engineering, then Bills of materials. Create a BOM or a new revision of one.
  2. Enter a Description ("What changed in this revision") and the Base quantity. The base quantity must be more than 0.
  3. Add lines. Each line has the component, quantity per base quantity, unit, scrap %, the operation that uses it, an issue method, and Phantom. You can add Reference designators such as "R1, R2, C5", a note, and alternates. Use indent, outdent, move, add, and remove on a row.
  4. Add drawings with Add drawings.
  5. Save, then click Release revision.

Issue methods

MethodMeaning
PickThe store brings it. The operator scans it.
BackflushTaken from line side when the operator reports.
Floor stockNever issued.

Rules

  • Lot- and serial-tracked items are always Pick. A backflush line for them is refused.
  • A phantom line needs a released BOM of its own.
  • A BOM that contains itself is refused.
  • A released revision cannot be edited.

If something goes wrong

MessageAction
The base quantity must be more than 0.Enter a positive number.
Fix the marked lines before saving.Correct the lines marked in red.
Not saved: the server found problems. They are marked on the lines.Correct and save again.
Someone saved this revision while you were editing. Their version is shown; make your change again.Repeat your change on the new version.