| Report | Shows |
|---|---|
| On-time completion | Orders finished by the due date. |
| WIP | Work in progress with its age. |
| Queue time and throughput | How long work waits and how much is made. |
| Yield and scrap | Good against scrapped quantity. |
| OEE and the six big losses | Overall equipment effectiveness. |
| Downtime | Stops by reason. |
| Labour efficiency | Time against standard. |
| NCRs | Non-conformance reports. |
| Schedule adherence and shortages | Plan against actual, and missing material. |
| Cost variance | Needs costs on and costs.read. |
OEE is availability times performance times quality. Planned downtime is not counted against availability.